Ongoing Projects
  • Project : Eklakhi-Balurghat (Capital)
    Anticipated cost (2017-18) : Rs.703.18 Cr
    Cumulative Expenditure : Rs.261.2 Cr
    Fund alloted (2017-18) : Rs.25 Cr.
    Expenditure (2017-18) : Rs.2.81 Cr
    Financial progress during (2017-18) : 11.25%
    Overall financial progress : 37.15%
  • Project : Dimapur - Kohima (Capital)
    Anticipated cost (2017-18) : Rs.2446.57 Cr
    Cumulative Expenditure : Rs.368.41 Cr
    Fund alloted (2017-18) : Rs.350 Cr.
    Expenditure (2017-18) : Rs.31.25 Cr
    Financial progress during (2017-18) : 8.93%
    Overall financial progress : 15.06%
  • Project : Agartala-Subroom (Capital)
    Anticipated cost (2017-18) : Rs.1740 Cr
    Cumulative Expenditure : Rs.2365.9 Cr
    Fund alloted (2017-18) : Rs.400 Cr.
    Expenditure (2017-18) : Rs.248.77 Cr
    Financial progress during (2017-18) : 62.19%
    Overall financial progress : 135.97%
  • Project : Jalalgarh-Kishanganj (Capital)
    Anticipated cost (2017-18) : Rs.359.86 Cr
    Cumulative Expenditure : Rs.3.13 Cr
    Fund alloted (2017-18) : Rs.50 Cr.
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 0.87%
  • Project : Bhairabi-Sairong (Capital)
    Anticipated cost (2017-18) : Rs.2393.48 Cr
    Cumulative Expenditure : Rs.1749.94 Cr
    Fund alloted (2017-18) : Rs.600 Cr.
    Expenditure (2017-18) : Rs.467.45 Cr
    Financial progress during (2017-18) : 77.91%
    Overall financial progress : 73.11%
  • Project : Sivok- Rongpo (Capital)
    Anticipated cost (2017-18) : Rs.359.86 Cr
    Cumulative Expenditure : Rs.648.33 Cr
    Fund alloted (2017-18) : Rs.250 Cr.
    Expenditure (2017-18) : Rs.2.44 Cr
    Financial progress during (2017-18) : 0.98%
    Overall financial progress : 180.16%
  • Project : Jogbani - Biratnagar(Nepal) (EBR)
    Anticipated cost (2017-18) : Rs.241.52 Cr
    Cumulative Expenditure : Rs.233.46 Cr
    Fund alloted (2017-18) : Rs.200 Cr.
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 96.66%
  • Project : Byrnihat - Shillong (Capital)
    Anticipated cost (2017-18) : Rs.4083.02 Cr
    Cumulative Expenditure : Rs.252.2 Cr
    Fund alloted (2017-18) : Rs.165 Cr.
    Expenditure (2017-18) : Rs.13.47 Cr
    Financial progress during (2017-18) : 8.16%
    Overall financial progress : 6.18%
  • Project : Kaliyaganj - Buniadpur (Capital)
    Anticipated cost (2017-18) : Rs.221.42 Cr
    Cumulative Expenditure : Rs.29.03 Cr
    Fund alloted (2017-18) : Rs.58 Cr.
    Expenditure (2017-18) : Rs.1.86 Cr
    Financial progress during (2017-18) : 3.2%
    Overall financial progress : 13.11%
  • Project : Balurghat - Hilli (Capital)
    Anticipated cost (2017-18) : Rs.242.22 Cr
    Cumulative Expenditure : Rs.56.07 Cr
    Fund alloted (2017-18) : Rs.200 Cr.
    Expenditure (2017-18) : Rs.10.71 Cr
    Financial progress during (2017-18) : 5.36%
    Overall financial progress : 23.15%
  • Project : Murkongselek-Pashighat (Capital)
    Anticipated cost (2017-18) : Rs.545.64 Cr
    Cumulative Expenditure : Rs.117.5 Cr
    Fund alloted (2017-18) : Rs.75 Cr.
    Expenditure (2017-18) : Rs.4.01 Cr
    Financial progress during (2017-18) : 5.35%
    Overall financial progress : 21.53%
  • Project : Dudhnoi-Mendipathar (Capital)
    Anticipated cost (2017-18) : Rs.247.75 Cr
    Cumulative Expenditure : Rs.309.23 Cr
    Fund alloted (2017-18) : Rs.5 Cr.
    Expenditure (2017-18) : Rs.1.3 Cr
    Financial progress during (2017-18) : 26.02%
    Overall financial progress : 124.82%
  • Project : Agartala- Akhaura(Bangladesh) (EBR)
    Anticipated cost (2017-18) : Rs.252 Cr
    Cumulative Expenditure : Rs.150 Cr
    Fund alloted (2017-18) : Rs.350 Cr.
    Expenditure (2017-18) : Rs.30 Cr
    Financial progress during (2017-18) : 8.57%
    Overall financial progress : 59.52%
  • Project : Dimapur - Tizit (SF)
    Anticipated cost (2017-18) : Rs.10 Cr
    Cumulative Expenditure : Rs.0 Cr
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 0.00%
  • Project : Lumding-Dibrugarh (Capital)
    Anticipated cost (2017-18) : Rs.787.92 Cr
    Cumulative Expenditure : Rs.788.55 Cr
    Fund alloted (2017-18) : Rs.0.01 Cr.
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 100.08%
  • Project : Lumding-Silchar (Capital)
    Anticipated cost (2017-18) : Rs.5114.91 Cr
    Cumulative Expenditure : Rs.7029.82 Cr
    Fund alloted (2017-18) : Rs.200 Cr.
    Expenditure (2017-18) : Rs.294.62 Cr
    Financial progress during (2017-18) : 147.31%
    Overall financial progress : 137.44%
  • Project : Katihar-Jogbani (Cap )
    Anticipated cost (2017-18) : Rs.725.54 Cr
    Cumulative Expenditure : Rs.567.1 Cr
    Fund alloted (2017-18) : Rs.40 Cr.
    Expenditure (2017-18) : Rs.8.72 Cr
    Financial progress during (2017-18) : 21.79%
    Overall financial progress : 78.16%
  • Project : Katakhal-Bhairabi (Cap )
    Anticipated cost (2017-18) : Rs.331.4 Cr
    Cumulative Expenditure : Rs.377.48 Cr
    Fund alloted (2017-18) : Rs.50 Cr.
    Expenditure (2017-18) : Rs.27.41 Cr
    Financial progress during (2017-18) : 54.82%
    Overall financial progress : 113.91%
  • Project : New Jalpaiguri-Siliguri-New Bongaigaon (Cap)
    Anticipated cost (2017-18) : Rs.1317.78 Cr
    Cumulative Expenditure : Rs.981.53 Cr
    Fund alloted (2017-18) : Rs.5 Cr.
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 74.48%
  • Project : Rangia - Murkongselek (Cap)
    Anticipated cost (2017-18) : Rs.3019.17 Cr
    Cumulative Expenditure : Rs.4346.7 Cr
    Fund alloted (2017-18) : Rs.150 Cr.
    Expenditure (2017-18) : Rs.88.7 Cr
    Financial progress during (2017-18) : 59.13%
    Overall financial progress : 143.97%
  • Project : Aluabari - Siliguri (Cap)
    Anticipated cost (2017-18) : Rs.485 Cr
    Cumulative Expenditure : Rs.437.65 Cr
    Fund alloted (2017-18) : Rs.17 Cr.
    Expenditure (2017-18) : Rs.2.09 Cr
    Financial progress during (2017-18) : 12.29%
    Overall financial progress : 90.24%
  • Project : Lumding -Hojai Patch Doubling (Cap)
    Anticipated cost (2017-18) : Rs.10 Cr
    Cumulative Expenditure : Rs.0.3 Cr
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 2.99%
  • Project : Kumarghat-Agartala (Capital)
    Anticipated cost (2017-18) : Rs.1242.25 Cr
    Cumulative Expenditure : Rs.1489.69 Cr
    Fund alloted (2017-18) : Rs.125 Cr.
    Expenditure (2017-18) : Rs.73.6 Cr
    Financial progress during (2017-18) : 58.88%
    Overall financial progress : 119.92%
  • Project : New Guwahati - Digaru (Cap. Fund)
    Anticipated cost (2017-18) : Rs.37.5 Cr
    Cumulative Expenditure : Rs.37.5 Cr
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 100%
  • Project : Ambari Falakata-New Mainaguri (Cap)
    Anticipated cost (2017-18) : Rs.269.35 Cr
    Cumulative Expenditure : Rs.171 Cr
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 63.48%
  • Project : New Coochbehar - Samuktala Road (Cap)
    Anticipated cost (2017-18) : Rs.105.42 Cr
    Cumulative Expenditure : Rs.133.96 Cr
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 127.07%
  • Project : New Coochbehar-Gumanihat (Cap.)
    Anticipated cost (2017-18) : Rs.261.86 Cr
    Cumulative Expenditure : Rs.23.75 Cr
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 9.07%
  • Project : New Bangaigaon-Rangiya-Kamakhya (Cap.)
    Anticipated cost (2017-18) : Rs.1798 Cr
    Cumulative Expenditure : Rs.0 Cr
    Fund alloted (2017-18) : Rs.10 Cr.
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 0.00%
  • Project : Bongaigaon-Goalpara-Guwahati (176 KM) (Cap.)
    Anticipated cost (2017-18) : Rs.1 Cr
    Cumulative Expenditure : Rs.0 Cr
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 0.00%
  • Project : Digaru-Hojai (102 KM) (Cap)
    Anticipated cost (2017-18) : Rs.10 Cr
    Cumulative Expenditure : Rs.0 Cr
    Expenditure (2017-18) : Rs.0 Cr
    Financial progress during (2017-18) : 0.00%
    Overall financial progress : 0.00%
  • Project : Bogibeel Rail-cum-Road Bridge (Capital)
    Anticipated cost (2017-18) : Rs.4996.19 Cr
    Cumulative Expenditure : Rs.4837.3 Cr
    Fund alloted (2017-18) : Rs.300 Cr.
    Expenditure (2017-18) : Rs.264.86 Cr
    Financial progress during (2017-18) : 88.29%
    Overall financial progress : 96.82%
  • Project : Harmuti-Naharlagun (Capital)
    Anticipated cost (2017-18) : Rs.475 Cr
    Cumulative Expenditure : Rs.546.03 Cr
    Fund alloted (2017-18) : Rs.25 Cr.
    Expenditure (2017-18) : Rs.10.06 Cr
    Financial progress during (2017-18) : 40.25%
    Overall financial progress : 114.95%
  • Project : Jiribam - Imphal Road (Tupul) (Capital)
    Anticipated cost (2017-18) : Rs.5897.37 Cr
    Cumulative Expenditure : Rs.6275.72 Cr
    Fund alloted (2017-18) : Rs.1052.02 Cr.
    Expenditure (2017-18) : Rs.474.83 Cr
    Financial progress during (2017-18) : 45.14%
    Overall financial progress : 106.42%
  • Project : New Moynaguri - Jogighopa (Capital)
    Anticipated cost (2017-18) : Rs.2483.04 Cr
    Cumulative Expenditure : Rs.2619.95 Cr
    Fund alloted (2017-18) : Rs.260 Cr.
    Expenditure (2017-18) : Rs.163.88 Cr
    Financial progress during (2017-18) : 63.03%
    Overall financial progress : 105.51%
  • Project : Araria - Galgalia (Capital)
    Anticipated cost (2017-18) : Rs.532.87 Cr
    Cumulative Expenditure : Rs.919.06 Cr
    Fund alloted (2017-18) : Rs.50 Cr.
    Expenditure (2017-18) : Rs.2.23 Cr
    Financial progress during (2017-18) : 4.46%
    Overall financial progress : 172.47%
  • Project : Teteliya - Byrnihat (Capital)
    Anticipated cost (2017-18) : Rs.430.33 Cr
    Cumulative Expenditure : Rs.427.71 Cr
    Fund alloted (2017-18) : Rs.150 Cr.
    Expenditure (2017-18) : Rs.24.36 Cr
    Financial progress during (2017-18) : 16.24%
    Overall financial progress : 99.39%
View- current status of claims received in Accounts Department-NFR-CON through Bill Status under facilities menu. #Expenditure position as on 31-10-2017 for FY 2017-18 uploaded.
Welcome to Accounts Department
N. F. Railway (Construction)

      With an objective for the expansion of Railway network, contemplating on the concept of socio-economic development in N. E. Region adjoining the seven sisters viz. Assam, Arunachal Pradesh, Nagaland, Mizoram, Meghalaya, Tripura and Manipur through railway connectivity as a part of Government policy Construction Organization in N. F. Railway was set up in the year 1979 and since then this organization achieved many milestones and striving hard for atta

Recent events and updates
FA & CAO/CON's Message

This web portal is launched with the aim of facilitating information on real time basis to our valued customers and is a small step in making Construction Accounts a paperless office

Quick Link
Copyright : 2014 | N.F.Rly (Con). ACCOUNTS DEPARTMENT | Disclaimer
Designed and Developed by Mr. Angshuman Sarma & Mr. Parag Moni Sarma.
Best viewed in 1024 x 768 resolution in Mozilla Firefox/Google Chrome or higher.